Broadrake Bunkbarn - Week 55 9th-13th Nov 2015

The start of the week sees the tiler prepare all the cubicles with aquapanels, batten out and measure up and the first cubicle is tiled up to the border of slate mosaic tiles
Storm Abigail produces very heavy downpours all day, and half way through the afternoon, Wonder of Wood e-mailed me this pic of Philpin Lane when they tried to make a delivery......they should have rung first!!! So Mike had to come home early in order to get the tiler back into Ingleton via Ellerbeck!

 one and half cubicles done by end of day two....
.... the next one along by Weds lunchtime, after which yet more rain stopped play and the tiler left site whilst the lane was still clear.

the wood flooring Take 2 comes to site on Thursday......
 neatly stacked

and the incorrectly finished flooring leaves site....
 Full van again - the guys then will have to unload it all from the van once back to base.....they'll have longer arms at the end
 meanwhile more tiles go up.....

 the toilet cubicles get the lowest layer of tiles in place
 and the combined shower/toilet room gets panelled out in readiness for next week
 over the weekend, Mike continues to take the wood upstairs to acclimatise; the ground floor heating is turned off in readiness for the slate flooring to go in

 and on Sunday, the rooms have a really good sweep and slates go onto battens so that the floor can be sealed to remove the dust...