The start of the week still saw reasonable amount of water where it wasn't really wanted.....
water pumped out....
and foundations for walls now dug out all the way round at end of the day
Tuesday saw the concrete arrive....beast of a machine
building site with a view
the concrete wagon driver was very worried about reversing back out....but it was easy peasy
The telehandler was on site by mid-week to move the roof pallets up to site with trailer to help
telehandler lays out the roof slates in size order ready for easier access once roof work starts
more big wagon excitement followed at the end of the day as more blocks arrived in the dark....
ready for more blockwork onto the footings the next day....
note the temporary roof drainage in place