Broadrake Bunkbarn - Week 42 10th-14th August

This week work boarding out work moves downstairs 
- delivery of 40 plaster boards in readiness


double boarding over beams


and upstairs the final plaster skim starts on the ceiling 



the old floorboards have been through Wonder of Woods (Stainforth) sanding machine and router in readiness for us to glue them together into window sills

 first plaster starting to dry out

 door casings go in downstairs

wall over door framed out

all boarded out in downstairs rooms




and upstairs the ceiling is fully plastered





.... and the small room too

after a miserable day of heavy rain, the rain clouds linger
 and Ingleborough is out of sight

finally, the park bench is back out front now that the field has been mown

house martin babies have been heard, but still not yet seen....must spend more time looking