This week has seen the first of the winter weather - snow just on the tops on Monday, but at ground level by Friday. In between, heavy hail showers and strong winds....
Work focused on the washroom re-build, widening of the old original doorway and more underpinning on the east gable end externally and internally
internal lintel and new brickwork in place
but builders made it to site after several attempts to get up the icy steep slope on Philpin Lane
Work focused on the washroom re-build, widening of the old original doorway and more underpinning on the east gable end externally and internally
....old lintels from original doorway are removed - an old original stone gate post
and wooden central part now quite rotten......definitely don't meet building regs....
Day 41 new front doorway
Work continued through wet, very cold and windy days....steel beam now back in place
By Friday this week, more serious snow
but builders made it to site after several attempts to get up the icy steep slope on Philpin Lane
More underpinning on east gable end - externally
and internally
and late afternoon sunshine on snowy fields across to viaduct to end Week 9